Monday, November 15, 2010

Frames and Roof Trusses are up


The roof trusses are done most of the windows are in and the plumbing has been routed through the frames.

house progress

preparation for slab






formwork in progress










Slab completed









Start of the frames

Thursday, November 4, 2010

Our New Home



Masterton Manhattan 39 with 5th Bed ensuite option and Alfresco.Trend Facade and lots of our own Design Additions


The original 1950's house
Contracts signed 16/6/10 
Demolition of old house 3/8/10
Pool roughed in 28/10/10
Slab poured 18/10/10
Frames delivered 26/10/10